Construction of Reinforced Earth Wall at Resa 07 side in progress as on 20.02.2017
Construction of Rein...
Download
Construction of Operational Perimeter Road near Resa 25 in progress as on 20.02.2017
Construction of Oper...
Download
Structural work of Fixed Finger Installation of Passenger Boarding Bridge in progress as on 16.02.2017
Structural work of F...
Download
Laying of WMM Wet Mix Macadam at Car Park area in progress as on 16.2.2017
Laying of WMM Wet Mi...
Download
Roofing work of Passenger Terminal Building in progress as on 15.02.2017_1
Roofing work of Pass...
Download
Construction of MBBR(Moving Bed Biofilm Reactor) Tank of Sewage Treatment Plant in progress as on 15.02.2017_1
Construction of MBBR...
Download
Construction of Car Park area in progress as on 13.2.2017
Construction of Car ...
Download
Construction of Planter Box above Flyover in progress as on 13.2.2017
Construction of Plan...
Download
Profiling & Lifting of Aluminium Roofing Sheet of Passenger Terminal Building in progress as on 09.02.2017
Profiling & Lifting ...
Download
Laying of WMM(Wet Mix Mecadam) at Operational Road near Fire Station(East) in progress as on 08.02.2017
Laying of WMM(Wet Mi...
Download
Construction of Motor Transport Workshop in progress as on 08.02.2017
Construction of Moto...
Download
Structural work of Fixed Finger for installation of  Passenger Boarding Bridge in progress as on 06.02.2017_1
Structural work of F...
Download
Laying of DBM(Dense Bituminous Macadam) in progress at RA2-RA3 in progress as on 06.02.2017_1
Laying of DBM(Dense ...
Download
Site visit of Ex.Central Civil Aviation Minister Shri.C.M Ibrahim on 04.2.2017_1
Site visit of Ex.Cen...
Download
Site visit of Ex.Central Civil Aviation Minister Shri.C.M Ibrahim on 04.02.2017_1
Site visit of Ex.Cen...
Download
Site visit by BSNL Team on 03.02.2017
Site visit by BSNL T...
Download
Construction of Passenger Terminal building in progress as on 03.02.2017
Construction of Pass...
Download
Site Inspection by Chief Commissioner of Customs Shri.Pullela Nageswara Rao, Commissioner of Customs Shri P.V.N.Suresh Babu and Team on 02.02.2017
Site Inspection by C...
Download
Inspection of Customs facilities at Passenger Terminal Building by Chief Commissioner of Customs and team on 02.02.2017_3
Inspection of Custom...
Download
Inspection of Customs facilities at Passenger Terminal Building by Chief Commissioner of Customs and team on 02.02.2017_2
Inspection of Custom...
Download
Inspection of Customs facilities at Passenger Terminal Building by Chief Commissioner of Customs and team on 02.02.2017_1
Inspection of Custom...
Download
Construction of DVOR Building nearing completion as on 02.02.2017
Construction of DVOR...
Download
Construction of Meet & Greet area at 102 m level of Passenger Terminal Building in progress as on 02.02.2017
Construction of Meet...
Download
Sewage Treatment Plant work in progress as on 01.02.2017
Sewage Treatment Pla...
Download
Structural work of Ramp from 113m level to 108m level in progress as on 01.02.2017
Structural work of R...
Download
Roofing work of Passenger Terminal Building in progress as on 01.02.2017
Roofing work of Pass...
Download
Construction of Car Park area in progress as on 30.01.2017
Construction of Car ...
Download
Construction of DG Yard in progress as on 28.01.2017
Construction of DG Y...
Download
Frame work of glass lift in progress at 102 lvi in progress as on 28.1.2017
Frame work of glass ...
Download
Truss work of PTB Meet and Greet Area Canopy in progress as on 24.1.2017
Truss work of PTB Me...
Download
 
 